Construction Projects

August - November 2023
Work in Progress

Several sanitary sewer and road construction projects will begin in mid August and continue through November. Please visit use the links below for more detailed information.

Road Reconstruction Projects - tentative timeframes:

Beginning 9/19/23 and taking approximately 3 weeks to complete:
  • Crooked Hill Rd
  • Rose Hill Rd
  • Valley Rd
  • Goose Valley Road
  • Locust Lane
  • Maple Shade Rd
Specific locations and additional projects and timeframes can be found here:

SQT Constructions Projects - Public (arcgis.com)